NAMA announces details of Docklands and residential funding programmes
DOCKLANDS | NEW HOMES |
3.8 million square feet of commercial space – equivalent to double the original IFSC | Focus on 3 and 4-bed starter homes |
€170m funding plan for Boland’s Quay offices, apartments and shops announced today | 20,000 new homes |
15 separate sites in North and South Docklands 2,000 apartments | 78% in Dublin city and county 22% in other areas of strong demand in ROI Total 93% in Greater Dublin area |
Up to 30,000 construction and ancillary jobs generated by the Docklands and new homes funding programmes |
"NAMA has committed itself to funding the delivery of much-needed office space and quality homes and, in doing so, it hopes to leave a lasting and positive legacy for the coming decades." – NAMA Chairman Frank Daly
"This funding programme is designed to maximise the return to Irish taxpayers on NAMA’s secured assets. These are commercial ventures and they will also contribute to making the Dublin Docklands a better place to live, work, invest and create jobs. We are on track to make a significant contribution to delivering large numbers of quality new homes where people need them but it will still only be 20% of the forecast market demand." – NAMA Chief Executive Brendan McDonagh
Thursday 3rd December 2015
The National Asset Management Agency (NAMA) has today announced details of a major funding programme that aims to deliver almost 4 million square feet of new commercial space in Dublin Docklands and 20,000 new homes in Dublin and other areas of strong demand. The residential programme will require total funding of €5.6 billion with peak funding expected to be €1.8 billion - the proceeds from the sale of completed projects will be recycled to fund new commercially viable projects. The Docklands development programme will require total funding of €1.9 billion with peak funding up to €500m.
In an effort to de-risk these programmes and to maximise the contribution of the alternative funding, development and construction sectors, NAMA will look for JV partners interested in the co-funding and construction of projects. With that in mind, NAMA will formally seek, in January 2016, ‘expressions of interest’ from potential partners for its residential delivery programme.
In line with NAMA’s obligations under Section 10 of the NAMA Act, all projects will be required to pass a stringent commercial viability threshold before NAMA approves funding. The Agency will explore appropriate financing options for each site to establish the best financing mechanism specific to each. These options include NAMA funding all of the construction work required; co-funding with other lenders; or establishing project-specific joint ventures with major investment or construction groups. NAMA will also work with non-NAMA building platforms.
The funding programme is expected to generate up to 30,000 jobs when construction is at its peak and deliver commercial space equivalent to approximately double the original IFSC.
NAMA is confident that the new programmes will not affect its plan to redeem all of its senior debt by 2018 and its subordinated debt by 2020. Current projections indeed indicate that the programmes are likely to increase NAMA’s projected terminal surplus (currently estimated at up to €1.75bn) which will be transferred to the Exchequer when NAMA completes its work.
The announcement was made today at the formal launch of NAMA’s funding programme in Dublin, which was attended by Minister for Finance Michael Noonan TD and Minister for Public Expenditure and Reform Brendan Howlin TD, and hosted by NAMA Chairman Frank Daly and NAMA Chief Executive Brendan McDonagh.
Today’s announcement provides detailed information on some of the projects that are included in the two programmes.
Michael Noonan, Minister for Finance, said:
"NAMA’s commitment to the Dublin Docklands SDZ combined with its efforts to provide much needed supply of residential units will continue to encourage Start-Ups and Multi-Nationals alike to have confidence in identifying Dublin as the home of choice for their businesses and will allow us to continue to punch above our weight in the global competition to attract and retain talent.
On the residential side, today’s launch follows on from an announcement I made in my Budget speech that NAMA would be in a position to provide 20,000 additional housing units by 2020. This, in addition to the housing package announced recently by Minister Alan Kelly, demonstrates this Government’s commitment to addressing the housing shortage which is particularly evident in the greater Dublin area.
I want to take this opportunity to thank the entire NAMA team for its continuing and tireless efforts to bring about such an important contribution to the recovery of the State".
Brendan Howlin, Minister for Public Expenditure and Reform, said:
"I commend NAMA for taking this considered commercial decision which will ultimately benefit the taxpayer. It is welcome both in terms of the Housing and Commercial Development resulting from these programmes and in terms of the enhanced return to the taxpayer these programmes will secure.
I look forward to seeing the SDZ come to life. I also look forward to the positive impact on the housing market your residential funding programme will have.
Judging by today’s presentations, both will be remarkable achievements."
Frank Daly, NAMA Chairman, said:
"NAMA has committed itself to funding the delivery of much-needed office space and quality homes and, in doing so, it hopes to leave a lasting and positive legacy for the coming decades."
We are proud to be in a position to use NAMA’s unique blend of property and financial expertise, funding capability and scale to benefit the taxpayers the Agency was set up to serve."
Brendan McDonagh, NAMA Chief Executive, said:
"We are making the Dublin Docklands a better place to live, work, invest and create jobs and are on track to make a significant contribution to delivering large numbers of quality new homes where people need them.
This is an ambitious commercial programme but we are confident that we can deliver. We look forward to building on our successful track record of creating significant value for the taxpayer and asset managing our secured assets in the best way possible."
Key features of Dublin Docklands SDZ programme
- 15 major new city blocks
- Almost 4 million square feet of office space
- 66,000 square feet of retail space
- 2,000 new homes
- 13,000 sq. ft. of restaurant space (in schemes granted permission)
- 18,000 sq. ft. of new cultural and community space and high-quality civic plazas (in schemes granted permission or where planning has been submitted)
- 1 major new street
- Building cross-river access to DART rail line from North Dockland
- Building cross-river access to LUAS tram network from South Docklands
- Ireland’s biggest-ever student accommodation block
- Dublin’s tallest office block
Dublin Docklands – progress summary
Construction work now underway – 3 sites | |
---|---|
8 Hanover Quay Boland’s Quay Capital Dock | 782,000 square feet 246 homes |
Planning permission obtained, construction work imminent – 3 sites | |
76 Sir John Rogerson’s Quay 5 Hanover Quay Project Wave (North Wall Quay) – Phase 1 | 608,000 square feet 161 homes |
Planning applications submitted – 5 sites | |
City Quay Spencer Dock – Phase 1 EXO Building, Point Village Block 5, Point Village Block 10A, Point Village | 1.2m square feet 450 homes 169-bedroom hotel |
Planning applications nearing submission – 6 sites | |
Project Wave (North Wall Quay) – Phase 2 Spencer Dock – Phase 2 10-12 Hanover Quay Block 19 (Waterways Ireland) Block 3, Mayor Street Block 9, North Wall Quay | 1.3m square feet 1,200 homes |
Key features of new homes funding programme
- 20,000 new homes
- 13,200 units already identified as commercially viable at this point; others to become viable following intensive planning and asset management work and infrastructural spending.
- Focus on 3 and 4-bed starter homes
- Programme will include high-quality dual-aspect apartments in city centre locations
- 78% will be in Dublin
- 15% will be in counties Meath, Kildare and Wicklow
- 7% in other areas where demand is proven
Locations will include:
BALDOYLE / CLONGRIFFIN CLUSTER | NO. UNITS | STEPASIDE / FOXROCK CLUSTER | NO. UNITS |
Under Construction | 315 | Under Construction | 59 |
Planning Granted | 146 | Planning Granted | 115 |
Planning Lodged | 0 | Planning Lodged | 446 |
Planning to be Lodged within next 12 months | 609 | Planning to be Lodged within next 12 months | 341 |
Total | 1070 | Total | 961 |
|
|
|
|
DUN LAOGHAIRE CLUSTER | NO. UNITS | PELLESTOWN / ASHTOWN CLUSTER | NO. UNITS |
Under Construction | 197 | Under Construction | 237 |
Planning Granted | 667 | Planning Granted | 279 |
Planning Lodged | 0 | Planning Lodged | 318 |
Planning to be Lodged within next 12 months | 0 | Planning to be Lodged within next 12 months | 0 |
Total | 864 | Total | 834 |
|
|
|
|
SWORDS CLUSTER | NO. UNITS | KILTERNAN CLUSTER | NO. UNITS |
Under Construction | 115 | Under Construction | 0 |
Planning Granted | 72 | Planning Granted | 125 |
Planning Lodged | 551 | Planning Lodged | 106 |
Planning to be Lodged within next 12 months | 56 | Planning to be Lodged within next 12 months | 399 |
Total | 794 | Total | 630 |
|
|
|
|
|
|
|
|
BALLYCULLEN / KNOCKLYON CLUSTER | NO. UNITS | CASTLEKNOCK / DISWELLSTOWN CLUSTER | NO. UNITS |
Under Construction | 123 | Under Construction | 359 |
Planning Granted | 172 | Planning Granted | 0 |
Planning Lodged | 79 | Planning Lodged | 0 |
Planning to be Lodged within next 12 months | 180 | Planning to be Lodged within next 12 months | 74 |
Total | 554 | Total | 433 |
New homes – progress summary
| Status | Total |
TIER 1 sites | Completed – end 2015 | 2,300 |
| Under construction | 2,950 |
| With planning permission but not yet under construction | 4,900 |
| Sub-total | 10,150 |
TIER 2 sites | Planning applications lodged | 3,900 |
| Planning applications to be lodged within 12 months | 6,000 |
| Sub-total | 9,900 |
Grand Total | 20,500 |
Boland’s Quay development funding announced today
NAMA has today announced that it is providing €170m to fund the Boland’s Quay (formerly known as Boland’s Mill) project, which is being developed by Savills, a NAMA-appointed receiver, and which recently received planning approval.
NAMA is funding the demolition and enabling works phase at Boland’s Quay over the next 10 months and has committed to funding all construction work on the site, which is expected to be completed by Quarter 3 2018.
This project will include:
- 2 landmark office buildings of 274,000 square feet 41 apartments
- Retail and commercial space of 15,000 square feet
- Extensive restoration of protected structures
- 2 new civic plazas with water frontage to Grand Canal Dock
- A new pedestrian bridge to provide walking routes from Barrow Street/Google European headquarters through the site
- Cultural/community space of 5,910 square feet
Welcoming the announcement, Receiver Mark Reynolds of Savills, said:
"The development of Boland’s Quay is now full steam ahead. We are delighted with NAMA’s commitment to funding its construction, as it enables us to move forward with the certainty that our plans for the site will come to fruition. This will be one of the most significant construction projects this city has seen over the past 10 years and it has been supported by the SDZ fast-track planning scheme introduced by Dublin City Council, which has seen us bring the project from planning stages to development in less than a year."